Spiders

A new addition has appeared in the Ab Kettleby tower – a bell-rope spider!

Ab Kettleby is a home to a number of horses in the various stables and studs dotted around the village. The most famous of which would be Desert Orchid, who spent his summers in the village, and lent his name to help raise funds for the restoration of the church a few years ago.

Spider

So as a nod to Dessie, and our other equine neighbours, the spider has been formed from six horse shoes, each providing a hook for a rope. A welcome addition to the tower which is starting to feel a bit more ‘professional’!

Augmentation Christmas Update

First of all, apologies for the lack of news on the website over the last couple of months.* The augmentation is progressing, but progress has been frustratingly slow.

September seems such a long time ago when we excitedly received the bells at the church – at the time, it felt like real progress and it wouldn’t be many more weeks before we could be ringing.

The frame repairs were completed and all bells located in the correct place in the tower by the end of October. A couple of weeks later and the easy part of getting the existing three to a ringable state was completed. The ringers elected to return to the three bells at Ab Kettleby on practice nights, as the extended displacement was beginning to take its toll! So Wednesday night practices resumed in St James’ on 18th November 2015.

Because of the frame issues, the augmentation process has been ongoing much longer than anyone had anticipated. Which in turn means that various long-standing personal commitments from the volunteers have also prevented much progress in recent weeks.

bells 23-dec

That said, we are tantalisingly close to ringing all six bells. Some hard work today has seen two of the remaining three bells be fitted out and ready to ring! The second was up and running by about 17:00, and the tenor was completed at about 19:30.

So we had a bit of a delayed start to our Wednesday practice night while the tenor’s rope was adjusted to the correct length. (Not a problem – we had planned a more social night tonight, with tea/coffee and cakes galore to fill the void!!) We finally got going with some simple rounds on 5 bells – such a different sound and feel to the with the new tenor taking the peal to a major key!

The treble bell still needs a bit of adjustment to its frame position; then the pulley box, slider and stay need fitting, before the rope can be put in place and we can have our full peal of six. It doesn’t feel like there is much left to do. It was planned and hoped that we would be ringing them by Christmas this year, but disappointingly, some last minute hitches look likely to prevent the final few tasks from being carried out.

Good things come to those who wait..!

(* for more details, see BellBoard)

Building the new Treble’s pit

Saturday saw another step towards the completion of our augmentation project. Our volunteers spent a full day in the tower with the intention of getting the bells up into their pits. Unfortunately, a bit of a hiccup in the repair of the broken frame side meant that it wasn’t ready for the weekend, so the amount of work that could be done was limited.

First, attention was given to the new treble pit. A new section of beam was to be installed first. A section of wall was removed to allow the beam to be anchored into the brickwork. As we did so, it revealed the end of a beam running the full width of the tower. During the clean down and restoration of the frame, we could not find any evidence of paint or preservation of the steel work, so considered that there probably hadn’t been any! However, the reveal of the beautifully preserved beam end, which has been protected from the weather embedded in the wall for 65 years, showed that the beams at least were painted up with black paint.

The newly painted red section of beam contrasts with the preserved black section inside the wall.

The newly painted red section of beam contrasts with the preserved black section inside the wall.

The new beam section was put in place and propped up with with wood and the brand new frame side (which was hoisted up in June!) could now finally be put in place. Once secured, the new treble was lifted in to its new home and bolted in place. The hole in the wall was then filled with concrete to complete the installation of the beam. There are still some braces to be installed around the new treble area to reinforce the the frame and control the additional forces that will be exerted when the bells are rung full circle.

Next, attention was turned to the new heavy tenor. The tenor’s pit was already in place, so the operation was much more straightforward. Additional acrow props were put in place underneath the lifting beam to reduce the span of the load. The tenor slowly made its way up to the bell-chamber and a second chain block helped to manoeuvre it to its new home at the back of the tower.

There are still two bells in the intermediate chamber waiting to be hoisted up, but it’s exciting to see that two thirds of the bells are now more or less in their final positions!

The Bells Are Back!

Last Tuesday saw 5 bells being delivered to St James’. The two old bells that were taken away for tuning and repair were joined by their new siblings; two brand new trebles and the tenor bell which has been relocated from Cornwall.

On Tuesday afternoon, an 18T lorry, courtesy of sponsor Brands2hands, arrived at the John Taylor Bell Foundry in Loughborough and loaded our five bells, along with the new wheels, stays, sliders, clappers, pulley boxes and other various fitments. The bells were put onto pallets to make transportation easier and were taken back to Brands2hands’ warehouse in Old Dalby for onward transport to Ab Kettleby by smaller vehicles during the evening.

Loading the bells

The first bells and fittings arrived in Church Lane just before 17:30 to a patiently waiting crowd of local ringers. The first three bells to arrive were the smallest bells – the two new trebles, and the existing old treble – numbers 1, 2 and 3 of the new peal. They were unloaded from the van – the tail-lift and pallet trucks making short work of the process – and transferred to the church.

Number 3 returns

A ramp had been constructed to allow the step into the church to be navigated with ease.

Before we knew it, the first three bells were in the aisle ready to be winched up.

The first three bells arrive

First up was the new number 2.

_MG_5254
IMG_0923

Shortly followed by the number 3.
_MG_5501

And then the brand new treble.

_MG_5825

These bells only made it as far as the intermediate chamber, as the frame for them still needs to be constructed or reconstructed!

The two larger bells were fetched from Old Dalby in separate vehicles; the heavy tenor arriving on a trailer. The number 4 (old number 2) was taken off the van with the tail-lift, but we needed a special piece of equipment to take the new tenor from the trailer. Fortunately, help was on hand from a local farmer and his telescopic forklift – light work was made of moving the tenor from the trailer and a good way onto the path before pallet trucks took it the rest of the way to the church.

Telescopic forklift makes light work of moving the tenor

The Tenor

The number 4 was hoisted all the way up to the second floor and placed straight into its pit.

Then it was time for the tenor – we had already established that it wouldn’t be possible for the tenor to fit through the doorway into the base of the tower, so it needed to be lifted over the screen instead. Various combinations of winch were used in various different places, along with various people pulling on strops before eventually, with the help of a “chain pull”, the tenor made its gentle descent on the other side of the screen, before being slowly hoisted up to the intermediate chamber.

Tenor doesn't fit through the door

With that it was nearly 10pm, so we called it a day and made a weary beeline for the Sugar Loaf for some well deserved refreshment.

Rust

While the frame and beams are being repaired, and tuning of the two removed bells is taking place, the bell chamber is looking a bit empty. Therefore, it’s an ideal opportunity to clear up the debris that’s been created by recent works, treat and prime the newly exposed metalwork, and prepare for a top coat of paint. Here’s the rather empty looking bell chamber

Empty Bell Chamber

Also, here is a closer view of the rust and corrosion that we’ve been faced with. This is the beam between underneath the fractured frame side that supported the current tenor. The loose surface rust has been removed, and the surface stabilised ready for priming, but the erosion is very noticeable.

Corrosion on beam

This is a bolt which held the frame side to the above beam. The frame side sits on ‘feet’ on top of the beam, so there is a gap between beam and frame side where the bolts hold everything together. Weather is, of course, able to get into the gap – the bolt clearly shows the difference between exposed and non-exposed metal work.

_MG_4064

Treble’s going, she’s gone!

Work continued apace last night as the problem beam was removed, enabling all the heavy items to be winched down. The treble was first, shortly followed by the second, and finally the broken frame side. The beam itself had to be cut, so that has also been taken away for restoration/repair.

Treble's going

"Treble's Going" - Peter Hayward supervises as the Treble is lowered into the Ringing Chamber

The Second is lowered through the intermediate chamber

Treble and Second made it safely down

The treble and second will receive some light tuning to bring them into line with the other old and new bells. They also need new 'pads' (the section between bell and headstock) due to more weather related deterioration.

 

The frame side is also planned work - it was noted on a previous inspection, that the rust build up and expansion between the cast iron frame side, and the beam it sits on, had caused a fracture in the iron casting. While the bells aren't particularly heavy and leaving it in situ was, structurally, a valid option, it was felt while other bells were being removed, the opportunity to fix the frame shouldn't be neglected. Somewhat inevitably, this too also proved troublesome to dislodge. It's difficult to convey how much damage the rust has caused, but numerous nuts and bolts proved impossible to shift, the rust having effectively welded all the steel together! The trusty angle grinder was pressed into action once more.

Sparks fly as Carl from Black Cat Ironworks cuts through the rusted bolts

Sparks fly as Carl from Black Cat Ironworks cuts through the rusted bolts

Finally the bells and frame sections were hauled along the narrow paths and loaded into to the van. A heavy rain shower arrived just in time to give the treble another soaking - certainly no worse than it's seen in the tower.

Loading the Second

Loading the Second

She's gone.

She's gone.

Work In Progress

This weekend saw the last bits of the platform that was resting on the bell-frame dismantled. The platform will be restored at a higher level, thus allowing our new bells to be hung beneath it. Here’s a view of the situation in the bell chamber at the moment. The frame has been partially dismantled, and the treble is waiting to be lowered once the problem beam underneath has been removed.

 

20150725_174336

 

 

Augmentation work update

A quick update on augmentation progress – our existing bells have now been dismantled, ready to be removed for the work that’s needed on them, and our new bells are completed and ready at the foundry doors to be shipped out to us!

However, the frame isn’t quite ready for them yet. A section needs to be removed to allow the bells to taken out and put back again. Unfortunately, the bells are just a bit too big to fit through the gap without partially dismantling the frame. Which is where a significant problem has been encountered – 50 years of weather in the spire has taken its toll on the bell frame, and the piece we need to remove has borne the brunt of the leaks over the years. The rust means that a section of RSJ is proving incredibly difficult to take out, and thus far has thwarted attempts to remove the existing treble.

 

Work Finally Underway

Amid much delight, work has finally started on installation of the new bells and the frame to support them!

The new frame side and repaired steel work, which was taken off the frame in April, arrived back in Ab Kettleby last night along with lifting gear to raise the heavy components to the bell chamber. The lifting gear was installed, and hatches opened in the tower. Here’s the missing frame side making its way up:

Hoisting the New Frame

Hoisting the New Frame

As work has now started, it is not possible to ring the bells until the work is complete. That means no Sunday Service ringing at Ab Kettleby. We will continue a weekly practice night but at a different local tower. Keep an eye on the website/Twitter/Facebook for updates.

The next step work will be to remove the treble and second so they can be taken to the foundry to carry out the the work that is required on them. All being well, it is anticipated that the project should be complete by the beginning of August.

One Year On

SallyIt is exactly one year ago today that regular Wednesday evening ringing practice started. We’ve come a long way in 52 weeks; four of the six ‘recruits’ we started teaching that day have become efficient and competent bell ringers and form a core part of the team.

We’ve also recruited seven others along the way – some more recently than others, so there are various stages of teaching and learning going on all the time!

Of course, getting the ringers up to speed wouldn’t have been possible without the invaluable assistance from three experienced ringers/teachers from neighbouring towers.

At last night’s practice session, we raised a glass in celebration of the achievements of the band, and a toast to the future and augmentation of Ab Kettleby Bells.

Cheers!